Shipment Statuses
We apologize for any delays in the shipping process. We are well aware that communication is key in order to make a pre-order successful. This section exists to keep you in the loop with the current status of the shipments of the 48v100ah batteries.
5/6/2022 Arrived at Current Connected HQ. Pallets loading and shipping Monday.
5/2/2022 Shipment cleared customs. An official warehouse delivery date of 5/6/2022 has been established. We anticipate shipments to depart warehouse on Monday 5/9.
4/18/2022 An updated ship arrival date of 5/1 has been provided.
3/30/2022 Ship has departed the port. Estimated arrival is 4/29/2022
3/24/2022 Shipping container picked up on time and in transit to the port.
3/20/2022 Shipping container loading completed, scheduled for pickup 3/22/2022
3/19/2022 Shipping container has arrived for loading.
3/17/2022: All goods ready for shipping.
3/16/2022: All testing complete, begin packaging.
3/8/2022: Assembly complete, all units currently in capacity testing department. Rack production has been completed.
3/02/2022: Metal box production has been completed. Earliest possible container booking has been confirmed for 3/19/2022 arrival at the factory.
2/24/2022: Cells have arrived to the factory for assembly.
2/14/2022: Metal box production has notified us of a 14 day lead time due to an issue with the the paint.
2/13/2022: Production was delayed by 2 weeks to coordinate appropriate changes. Production ready to proceed.
1/30/2022: Production halted due to an emergency design update; a different circuit breaker is being selected (with appropriate DC rating) as well as a change to the BMS to allow communications with additional inverters. Interconnection bus bars being changed to laminated flexible-type.
1/29/2022 Design released for production.
1/25/2022 Final prototype received for testing
1/11/2022 Final prototype shipped for testing
5/2/2022: Port arrival date has been updated to 5/12/2022.
4/8/2022: Container is in transit with an estimated port arrival date of 5/9/2022
4/4/2022: Container has been picked up and is en-route to the port.
3/30/2022: Shipping container arrived for loading. Pickup scheduled for 4/4.
3/29/2022: Ready for shipment.
3/28/2022: Capacity testing completed, prepare for shipping.
3/22/2022: Production completed, all units in capacity testing department.
3/17/2022: Metal box production has been completed. Container booking has been confirmed for 3/30/2022 arrival at the factory.
3/11/2022: Release for production